Ninth Project

 

 

Tajikistan 2003

  

NOC: Tajikistan

Contract signed on: 17 February 2003


Financial Support:

From: OCA                Amount: 50,000 USD      Date: 28 May 2003
From: Daimler Chrysler   Amount: 50,000 USD      Date: 06 June 2004

Project information:

Name: Olympasia Project, Kylyab
City and Province: Khatlon Region, 200km away from Dushanbe

Project Details:

Size: 200m x 400m
Number of rooms: 2 changing rooms, 2 shower rooms, 3 toilets, 2 rest rooms, 2 conference hall, 2 tribunes, 4 Administration / class room, 10 commercial rooms around the stadium.

Other facilities: Reconstruction of Kylyab Stadium. Facilities for Athletics, Tennis, Table Tennis, Wrestling, Boxing and Football.

Date of commencement: March 2003

Date of Completion: 13 May 2004

Status: Completed and Operational

Remarks: