NOC:
Philippines
Contract
signed on:
07 April 2007
Financial Support:
From:
OCA
Amount: 50,000
USD
Date:
27 April 2007
From:
Daimler Chrysler
Amount: 50,000
USD
Date:
25 September 2007
Project
information:
Name:
Philsports Complex
City and
Province:
Meralo Avenues, Pasig City 1603
Project
Details:
Size:
549.26 m2
Estimated construction cost:
120,000
USD
Other
facilities:
Renovation of the existing
facilities on the 3rd floor of the NOC HQ, which is consist
of: Conference room, President's room, Viewing room,
Chairman's office, library etc...
Date of
commencement:
16 May 2007
Date of
Completion:
15 August 2007
Status:
Functioning
Remarks:
|