Second Project

 

 

Jordan 2001

  

NOC: Jordan

Contract signed on:


Financial Support:

From: OCA                Amount: 50,000 USD      Date: 07 July 2001
From: OCA                Amount: 50,000 USD      Date: 18 February 2003

Project information:

Name: OCA Olympic Center
City and Province: Na'our town, Amman

Project Details:

Size: 900 m2 covered area
Number of rooms:

Other facilities: 1 out door artificial turf play ground, 1 multi purpose hall, administration office, library, 4 lavatories, 4 changing rooms, computer labs, workshops etc.

Date of commencement: 06 June 2001

Date of Completion: 01 February 2003

Status: Completed and Operational

Remarks: